National gas transmission company Transgaz announces having kicked off on Monday the construction of the BRUA pipeline, a project of national interest, namely Phase I, according to a press release by the Ministry of Economy.
Transgaz is building the infrastructure on Romania's territory, from the Bulgaria-Romania-Hungary-Austria corridor, Phase 1 (BRUA - Phase I) - project backed by the European Commission, important at a national and regional level, due to the fact that it diversifies gas sources.
The BRUA Phase 1 project includes the construction of the Podisor-Recas natural gas transmission pipeline, 479-kilometer long, with a diameter of 32 "(Dn 800) and a design pressure of 63 bar.The estimated total value for Phase I is of 478.6 million euro.
Within the BRUA Phase 1, Transgaz has already been working, since April 14, on the three compression stations, from Podisor, Jupa and Bibesti, where 40 percent of eligible expenses are covered by the European Union, through a grant worth 179.3 million Euro.
Economy Minister Danut Andrusca declared himself satisfied of the way Transgaz has managed until now the works for the BRUA project and underlined the importance of keeping to the timetable of the works.
Transgaz CEO Ion Sterian stated, in his turn, that the national gas transporter has the necessary resources and capacity to finalize the BRUA project, in compliance with the financial commitments and the time frame.
"We are rigorously monitoring both the works (...) at the pipeline and at the compression stations. We are in permanent contact with contractors in order to ensure that all works are on schedule and that they fulfill the necessary quality and safety standards. The BRUA segment on Romania's territory will allow us to cash in important sums of money from transport and transit tariffs," Ion Sterian, Transgaz CEO, stated.
Upon finishing the BRUA Phase 1 project, the two-way flow of natural gases will be ensured towards : Bulgaria - through the Giurgiu - Ruse interconnection, 1.5 billion Smc / year (171,000 Smc/h), 30 bar at the border and Hungary - through the Horia - Csanadpalota interconnectivity, of 1.75 billion Smc / year (200,000 Smc/h), at 40 bar at the border.
The BRUA Phase 1 project represents a priority at a national and regional level. It is included on the list of projects of the Central East South Europe Gas Connectivity (CESEC), because it brings a significant contribution to increasing safety in natural gases supply and the degree of regional interconnectivity.
Transgaz kicks off BRUA pipeline construction
Explorează subiectul
București
6°C
Articole Similare

1
Bolojan: Government to cut fuel excise, diesel prioritised
1

1
Presidential Administration hosts "Romania in the Spotlight" - debate on addictions among children and adolescents
1

1
Central bank governor: A prolonged Middle East conflict could have a severe impact on the economy
1

16
Nicusor Dan, on appointment of intelligence service heads: It is related to president and Parliament
16

10
As the Gulf crisis continues, we will have a slight increase in inflation in 2026 ( PM Bolojan)
10

17
Nicusor Dan: I don't think minority government would be appropriate solution for current times
17

30
Over 1 million accesses in the first hours on the eLicitatii.anaf.ro platform, launched on Monday
30

15
Nicusor Dan hopes nuclear energy will be supported by EU's future multiannual financial framework
15

13
Nicusor Dan: We hope that Romania becomes member of OECD in 2026; euro must be a goal
13

13
BVB stocks close Monday's trading session lower
13

18
Nicusor Dan,meeting with Roxana Minzatu: European project must focus, above all, on people
18

10
Romania's Cartarescu launches his latest novel 'Theodoros' in Luxembourg
10

9
Bank of Greece's Stournaras: Geopolitical conflict is a new supply shock for the global economy
9
















Comentează