Nuclearelectrica Chief Executive Officer Cosmin Ghita stated on Wednesday, at the Nuclear Power Plant in Cernavoda, that the refurbishment of Unit 1, an investment worth roughly 3 billion EUR, will ensure another 30 years of clean and viable energy under conditions of safety and economic efficiency.
"Today, we mark an essential moment for the nuclear industry in Romania, for Nuclearelectrica and for the power plant in Cernavoda, the inauguration of construction works within the refurbishment project of Unit 1. This is a major stage which has a dual significance, on the one hand, it crowns a chapter of almost 30 years of history and operation at the highest standards of excellence and safety, and, on the other hand, it opens the door to the future for reactor 1. Following the refurbishment, it will be modernized through the next-generation CANDU technology and will ensure another 30 years of clean and viable energy under conditions of safety and economic efficiency," Ghita stated at the opening of the refurbishment works of Unit 1 of the Nuclear Power Plant in Cernavoda.
According to him, the refurbishment project of Unit 1 has a strategic importance in ensuring Romania's energy security and entails "significant investments" which will support the national economic development.
"The total value of the ongoing investment is approximately 3 billion EUR and this project continues other refurbishment projects carried out at global level," Nuclearelectrica Chief Executive Officer stated.
Reactor 1 entered commercial operation in 1996 and produces 9 percent of the necessary of energy consumption at national level.
He stated that the refurbishment of Unit 1 brings substantial benefits.
Cosmin Ghita argues that there are plans to further increase production capacity through projects targeting reactors three and four.
"In addition, the refurbishment project, which will maintain the production capacity, we have ambitious plans to increase nuclear capacity to over 3,200 MW through the project of units three and four, four CANDU units and small modular reactors. The strategic projects for Romania are becoming a reality through sustainable and trust-based partnerships, with a strong support of national authorities and the involvement of some major external companies in the industry, and some international partners and financiers with a long-standing reputation," Nuclearelectrica head Cosmin Ghita stated.
Nuclearelectrica head Ghita: Refurbishment of Unit 1 will ensure another 30 years of clean and viable energy
Autor: Alexandra Pricop
Publicat: 03-09-2025 19:18
Articole Similare

18
Gov't okays contingent of 90,000 newly admitted foreign workers on Romanian labor market in 2026
18

14
The three Romanians stuck in cable car in Italy - evacuated in good condition (ForMin Toiu)
14

13
We will have a deficit lower than the 8.4% we aimed at (PM Bolojan)
13

18
European Commission transfers Tuesday over 586 mln euros to accounts opened at National Bank of Romania
18

9
Bucharest Stock Exchange (BVB) closes higher Tuesday's trading session
9

7
Net assets of investment funds increase by 3.2% in November
7

10
HealthMin announces establishment of AP-ROBOTICS; public hospitals equipped with surgical robots,financed for purchase of consumables
10

36
City Hall of Sector 1 finances modernization of Rapid Club's sports facilities
36

16
Consumer Protection levies fines of almost 679,000 lei on business operators in tourist resorts
16

11
Deficit reduction target will only be achieved through firmness in managing public resources (analysis)
11

14
Over 151 million euros from European funds for investments in vegetable and potato sector
14

19
Romsilva: 492 fires in state forests managed by Romsilva in the 11 months,damages estimated at 2.7 million RON
19

13
Draft law on prioritisation criteria for Anghel Saligny programme published in decision-making transparency system
13

















Comentează