The contract with Salini Impregilo to build segment no.3 of the Orastie - Sibiu Motorway has been cancelled, and a process to select a new company to remedy the deficiencies in that area will be started, with works to be completed in August, said Transport Minister Dan Costescu.
Under these circumstances, the traffic on the said motorway could be resumed in September this year.
"I have received a communication from CNADNR [the National Company of Motorways and National Roads] for the cancellation of the contract with the current constructor [for segment no. 3 of the Orastie-Sibiu Motorway]. At the same time, a new call for tenders for selecting the new constructor to fix the deficiencies will be launched. The deadline for these works, if no dispute arises, is August. That means in early or in mid-September, motorway traffic may be resumed," the transport minister told a Wednesday's conference at the ministry's headquarters.
A document of the Ministry of European Funds shows that the motorway in question has Q3 2018 as completion deadline and the remaining investment amounts to 92.4 million euros. AGERPRES
Contract with Salini Impregilo to build segment no. 3 of Orastie - Sibiu Motorway, cancelled
Explorează subiectul
Articole Similare

12
EnerMin Ivan:Final Investment Decision for Doicesti SMR marks transition from analysis implementation phase
12

8
ANAT vice-president: Romanian tourism is in technical recession
8

7
ECA's Romascanu: Romania has a relatively comprehensive RRF anti-fraud framework
7

7
Bucharest Stock Exchange closes higher in Thursday's trading session
7

6
Gov't spokesperson admits it's a difficult period for citizens, but essential for budget balance
6

9
Protest in Timisoara against postponement of Constitutional Court's decision regarding magistrates' pensions
9

6
The EP's view on cyberbullying and how realistic Romanian MEPs consider the proposed solutions
6

5
USR MPs call on European Justice Commissioner for more rigorous Rule of Law assessment
5

10
DefMin Miruta: National defense industry must be part of international production chains
10

10
EBRD sells Danube Logistics, operator of Giurgiulesti port in Republic of Moldova, to Constanta Port
10

29
National Audiovisual Council's decisions - confirmed by courts in proportion of 92% in last 10 years (institution's vice-president)
29

6
Romanian-Canadian cooperation in home affairs on agenda of talks between Minister Predoiu and Ambassador Buchan
6

6
Government temporarily suspends contracting procedure for projects financed by 2021-2027 Cohesion Policy
6

















Comentează